Construction Projects

Below are current road construction projects under design and/or construction.  Use the links below to view current construction projects and view construction project news releases.

  1. Major Street Reconstruction
  2. Local Street Reconstruction
  3. Construction Project News Releases

South Westnedge Avenue, Romence Road to Mall Drive:  Mill and resurface 4 inches of asphalt, concrete curb and gutter, sidewalks, ADA ramps, water main hydrant extensions, storm sewer improvements and traffic signal replacement at J L Hudson Drive. Storm sewer improvements includes replacement of existing storm lines and the installation of a storm sewer relief outlet for South Westnedge Avenue east of J L Hudson Drive.

Estimated  Cost: $3,000,000 (MDOT Funding - $700,000)
Construction Start Date: June 4, 2018
Anticipated Completion Date: September 14, 2018
Status: Underground utility and concrete work are complete.  Northbound lanes have been milled and resurfaced with a leveling course of asphalt.  Milling and paving operations on southbound lanes are scheduled to begin August 22, weather permitting.


West Centre Avenue, 12th Street to Oakland Drive: Mill and resurface 4 inches of asphalt, concrete curb and gutter, ADA ramps, extension of island boulevard left turn pockets in select locations, new sidewalk installation on south side from Old Centre Avenue to Oakland Drive, pedestrian push buttons, and traffic signal replacement at Oakland Drive. 

Estimated Construction Cost: $1,800,000 (MDOT TIP Funding - $1,300,000)
Construction Start Date: July 16, 2018
Anticipated Completion Date: September 28, 2018
Status: All underground utility work and 90% of concrete work has been completed.  Milling and paving operations of the leveling course of asphalt began August 12.

Oakland Drive, West Milham Avenue to I-94: Mill and resurface 4 inches of asphalt, concrete curb and gutter, sidewalks, ADA ramps, water main hydrant extensions at Hemlock Avenue and replacement of water main across Oakland Drive at Rosewood Avenue, installation of water lead and sanitary sewer manhole to service future development. 

Construction Cost: $549,239.25
Construction Start Date: June 25, 2018
Anticipated Completion Date: Week of August 20, 2018
 

Rockford Street, Schuring Road to Romence Road:  Mill and resurface 2 inches of asphalt, concrete curb and gutter, ADA ramps, storm sewer improvements and restoration. 

Estimated Construction Cost: $300,000
Construction Start Date: July 16, 2018
Anticipated Completion Date: September 2018
Status: Storm sewer improvements are complete.  Concrete work began August 14th.

Portage Road/Lakeview Drive Intersection Realignment:  Realign the intersection of Lakeview Drive and Portage Road to approximately 150 feet south, including concrete curb and gutter, sidewalk, ADA ramps, storm sewer improvements and the construction of Lakeview Court cul-de-sac. 

Estimated Construction Cost: $475,000
Anticipated Start Date: Fall 2018
Anticipated Completion Date: Spring 2019

Portage Road/Stryker Way Traffic Signal:  Installation of new traffic signal at Portage Road and Stryker Way with southbound deceleration lane for Stryker Way. Work includes installation of ADA ramps and pedestrian push buttons.

Construction Cost: $423,574.54 (MDOT TEDF Grant - $259,605.00/Stryker to fund balance)
Construction Start Date: March 26, 2018
Anticipated Completion Date: August 31, 2018
Status: New mast arms and poles have been installed.  Southbound right turn lane completed.


Oakland Drive/Vanderbilt Avenue Flashing Traffic Beacon:  Installation of new flashing traffic beacon at intersection of Oakland Drive and Vanderbilt Avenue. 

Estimated Construction Cost: $40,000
Construction Start Date: July 10, 2018
Anticipated Completion Date: September 14, 2018