Posted on: July 24, 2019

[ARCHIVED] Hampton Bog Pumping

portage michigan flag

UPDATE - AUGUST 6, 2019:  An average of 225 gallons per minute has been pumped over the last 13 days. The pumping, in conjunction with drier weather, has lowered the level of the Hampton Creek Wetlands 4.75 inches.  Listen to the Hampton Bog Pumping Update #3 Podcast.

**********

UPDATE - JULY 31, 2019:  The water level of the Hampton Bog has been reduced by more than two inches, with approximately 1.5 million gallons of water pumped into the storm sewer system. The water has receded back away from the adjacent properties between six to eight feet.  The city will continue to pump water from the bog in accordance with the emergency permit.  

**********

UPDATE - JULY 26, 2019:  As of 8 AM this morning, the city had pumped 370,000 gallons of water since starting the pump on July 24.  That in conjunction with evaporation had brought the water level down 0.6 inch.  As of noon today, with evaporation and pumping, the level of the bog is down a total of 1 inch.  The result is that the water has receded from the shoreline by one foot.  The city will continue pumping in accordance with the regulations.

**********

On July 24, 2019, the Michigan Department of Environment, Great Lakes and Energy (EGLE) Water Resources Division issued Permit Number WRP017481 to the City of Portage. The permit allows the city to temporarily place an intake pipe in and pump surface water from the Hampton Creek Wetlands at 7877 Moorsbridge Road.  

The city has begun pumping from the Hampton Creek Wetlands, which will continue for a period of 30 days. It is anticipated that approximately one million gallons a day may be pumped from the bog into the sanitary sewer system, which filters into the City of Kalamazoo wastewater treatment plant and eventually into the Kalamazoo River. The expectation is to reduce the bog by approximately 6 inches over the 30-day period. However, there are factors that might influence that, including rain events and groundwater levels. The 30-day pumping period is a short-term remedy and an experiment that will determine the ability to reduce water levels under current conditions.  

On Tuesday, July 23, the City Council awarded a contract to perform an environmental impacts evaluation for the Hampton Creek Wetland Area to Fishbeck, Thompson, Carr & Huber, Inc. The project will include a study of various engineering options for a long-term solution to the high water problem in the area.

Facebook Twitter Email

Other News in Spotlights

Community Services Openhouse 2023 1200

Community Human Services Open House

Posted on: September 29, 2023
Respect for Law Event 2023 News Flash_

Respect For Law Event

Posted on: September 28, 2023
Fire Prevention Open House 1_

Fire Prevention Week Open House

Posted on: September 28, 2023
Election Mail 2023 1200_

Absentee Ballots

Posted on: September 28, 2023
Website Bug

Council Capsule

Posted on: September 20, 2023
2023 09-15 Shaver Road Water Main

Shaver Road Water Main Installation

Posted on: September 15, 2023
PR 2023 - 2024 Online Brochure Fall Winter

2023-2024 Online Parks & Recreation Guide

Posted on: September 5, 2023
Community Art Award 1200 2023

Portage Community Art Award Exhibition

Posted on: August 31, 2023
Housing Task Force Social Media Graphic

Lake Center Housing Task Force

Posted on: June 8, 2023