Work to improve South Westnedge Avenue from Romence road to Mall Drive began on June 4 with milling of the roadway surface. Future improvements include new concrete curb and gutter, sidewalks, ADA ramps, water main hydrant extensions, storm sewer improvements and traffic signal replacement at J L Hudson Drive. Storm sewer improvements includes replacement of existing storm lines and the installation of a storm sewer relief outlet for South Westnedge Avenue east of J L Hudson Drive.
Estimated Cost: $3,000,000 (MDOT Funding - $700,000)
Anticipated Completion Date: September 4, 2018
Lane closures and traffic shifts began June 4, 2018 with construction work starting June 5, 2018.

To receive construction updates about this project, register for PortageAlert and select "2018 South Westnedge Avenue Reconstruction" subscription.
Visit the Construction Projects page to view all current construction projects. Questions about City of Portage construction projects can be directed to the Department of Transportation of Utilities by a contact form or at 269-329-4422.